Larry and his crew were up in Tilton on an Eversource job for the last week or so. They had to install approx 140′ of 3″ conduit from an existing riser pole to a meter bank. With the exception of locating an out of service leach field, it went very smooth....
Before the every other day snow started, Tim, Kevin and Mike were up north on a commercial project in Moultonborough. They were tasked with excavating and installing 260′ of schedule 80 conduit from an electrical pullbox to the customer’s existing house...