Went up to Laconia today to visit Larry, Troy and Wyatt on their current job site. They are installing approximately 320′ of 3″ conduit from an existing transformer to a new above ground handhole that they will install. They have some obstacles in the way...
We demolished a 54′ x 32′ farmhouse and a 56′ x 36′ barn for them. We also demolished and filled a well, partial concrete patio and concrete septic tank as well as the foundation of the old farmhouse. More to come but awesome job by everyone...