Went up to Laconia today to visit Larry, Troy and Wyatt on their current job site. They are installing approximately 320′ of 3″ conduit from an existing transformer to a new above ground handhole that they will install. They have some obstacles in the way...
Stopped by Tim’s crew in Grantham to see how things were going. They were on site to excavate and install about 100′ of 3″ conduit from an existing pole to the meter on the front of the residence. It was miserable out there but they did a great job...
Larry’s crew and sometimes more than his usual gang excavated and installed 4,800 feet of 4″ schedule 80 conduit. They also had to install 6 single phase vault structures and cut approximately 8 road crossings. We’ll be back in the spring for loam...
Excavation and installation of approx 150′ of 3″ conduit along with some steel conduit in one of the drainage swale. After the get a new hand hole installed, all that’s left is spring...
Larry and his crew were up in Tilton on an Eversource job for the last week or so. They had to install approx 140′ of 3″ conduit from an existing riser pole to a meter bank. With the exception of locating an out of service leach field, it went very smooth....